Updating Hours and Costs from Project Reporting and Travel Expense—Exercises
Basic Data Setup
Project Cost Element
Purpose: The purpose of this exercise
is to show you how to create project cost elements and connect them to code part
values.
Windows:
Project Cost/Revenue Elements
Project Cost/Revenue Element Per Code Part Value
- Create project cost elements which can be connected
to the accounts/code part values as derived by posting control rules. The posting control
rules relevant to reporting time, costs and travel expenses are shown in the
following table.
- Connect the relevant cost elements to the relevant
accounts/code part values. If your company has been created based on the STD company template
and no changes have been done to the default posting control rules or
mappings of cost elements to accounts, you will see the following mapping:
Posting Control Rule |
Scenarios when Posting Control Rule applies |
Expected Account |
Project Cost/Revenue Element |
PRJT1 |
Reporting time |
9170 |
LABOR |
PRJC1 and PRJC3 |
Report Cost |
9140 |
EXPENSES |
TX4 |
Report Travel Expense |
5800 |
|
- Map an appropriate cost element to account
5800 in order to update a project activity with costs from a travel expense.
General exercise for
Setting Up Project Cost/Revenue Elements
Required Data
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the
data that must be in place before you can perform the exercises below.
- Release the activities on which you want to report
hours and costs from project reporting and travel expense.
General exercise for
Executing
Activities
Main Exercise
Purpose: The purpose of these
exercises is to show you how
to update your activities for hours and cost from project reporting and travel
expenses.
Windows:
Project Navigator/Connections
Project Navigator/Activity
- Report
time and costs to your activities. (It may be helpful to report time on
one activity, and costs on another activity.)
- Open the
Project
Navigator window. Query for your project.
- In the Navigator, select the activities to which you
have reported time
and costs.
- Click the
Project
Navigator/Connections tab.
- Note that the project transactions are shown as connected objects on the
activity.
- In the Navigator, select the activity on which you have reported time.
- Click the
Activity tab.
- On the Hours tab, observe that the number of reported
hours are shown as Actual hours. There is
a value for used cost in the
Cost tab, which is equal to the number of reported
hours multiplied by the internal price for these hours.
- Verify that the cost
and hours updates the correct cost
element, based on how you set up the relevant posting control rule and cost
element mappings.
- In the Navigator, select the activity on which you have reported cost.
- On the
Cost
tab, observe that the reported cost is shown as Used cost.
- Verify that the used cost updates the correct cost
element, based on how you set up the relevant posting control rule and cost
element mappings.
- For your activities, note that the Actual Start Date field has a
value equal to the early start date. Observe that the Early Start Date
field is no longer editable.
- Optionally, change the actual start date and save your changes. Note that
the Early Start Date field is changed to be the same date as the
actual start date.
Note:
When the transaction updated as the time is reported, the cost related to it
will be updated as
General exercise for Report
Time and Costs
- Register a
travel expense to an activity. Continue processing the travel expense
until it is authorized.
- Open the
Project Navigator window. Query for your project.
- In the Navigator, select the activity on which you
have registered a
travel expense.
- Click the
Project
Navigator/Connections tab.
- Note that the project transaction is shown as a connected object on the
activity.
- In the Navigator, select the activity on which you have registered the
travel expense.
- Click the
Activity tab.
- On the
Cost tab, observe that there is a value for
used cost, which is equal to the travel expense cost, not
including VAT.
- Verify that the used cost updates the correct cost
element, based on how you set up the relevant posting control rule and cost
element mappings.
General exercise for
Register Travel Expenses