Netting Project Material—Exercises
IMPORTANT |
It is extremely important that you set up and work within your own
site to maintain your data integrity. If you work within any other site,
you will compromise your own exercise data as well as the data of other
students. Predictable exercise results require that your data be isolated
in your own site. |
Basic Data Setup
Inventory Location
Purpose: The purpose of this exercise is to show you how
to create an inventory location for the receipt of material into inventory. Material
in both the standard and project inventory will be held in this inventory location.
Windows:
Inventory Locations
- Create the following new inventory location at your site XX01, where XX
is your initials.
Location No |
Warehouse |
Location Name |
Location Group |
Location Type |
L1 |
A |
Stored |
30 |
Picking |
General exercise for
Entering Inventory
Location
Required Data
Registering Miscellaneous Demand to Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the main exercise below.
- For an activity or activities in your subproject structure, register a demand
for both standard planned and project-specific miscellaneous inventory
parts.
- Save your changes.
General exercise for
Registering Project
Demand
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the main exercise below.
- Release the activities which have connected miscellaneous demand which will
be netted.
General exercise for
Executing
Activities
Receiving Inventory Parts
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the main exercise below.
- Receive standard planned inventory parts into your site's standard inventory,
using your inventory location L1.
- Use the same inventory to receive a quantity of the project specific part
you want to net. Once this is done, Go to Inventory
Part In Stock window and query for this part for the project site.
Select this record, and then right-click and then click Transfer to Project
Inventory. In the dialog that appears, select from the list of values the
Project ID, Sub Project ID and Activity ID, then the Quantity to Transfer, and
then click OK.
General exercise for
Receiving Inventory
Parts (for standard planned parts)
Main Exercise
Purpose: The purpose of this exercise is to show you how
to net project material to meet the miscellaneous demands of the project.
Windows:
Project Navigator
Project Navigator/Demand/Misc.Part
Project Navigator/Supply/Reserved Materials
Project Navigator/Activity
- Open the Project Navigator
window.
- Query for your project.
- In the Navigator, select the activity or activities which have registered
miscellaneous demands (for both standard planned part and project specific part)
for which you would like to net the quantity required.
- Click the Demand
tab, and then click the Misc. Parts
tab.
- Check that the Netting check box-column for the demand line is selected
automatically by default.
- Go back to the Navigator and select the top node. Right-click, point to
Netting and then click Net Project Material. You can either run
netting on-line or as a background job. Click OK.
- Click the Reserved
Material tab and check that full or part of the required quantity
(depending on availability) has been automatically reserved for the miscellaneous
demands.
- Go back to the Misc. Parts tab and
check that the Reserved Quantity column has been updated with the quantity
that has been automatically reserved for the miscellaneous demand.
- Click the Activity
tab, and on the
Cost tab, observe that the Committed column has been updated
for the netted standard planned part. This value is based on the current part
cost for the reserved items.
- Verify that these values update the correct cost elements, based on how
you set up the posting control rule M62 and cost element mappings.