Issuing Material From Inventory—Exercises
IMPORTANT |
It is extremely important that you set up and work within your own
site to maintain your data integrity. If you work within any other site,
you will compromise your own exercise data as well as the data of other
students. Predictable exercise results require that your data be isolated
in your own site. |
Basic Data Setup
Inventory Location
Purpose: The purpose of this exercise is to show you how
to create an inventory location for the receipt of material into inventory. Material
in both the standard and project inventory will be held in this inventory location.
Windows:
Inventory Locations
- Create the following new inventory location at your site XX01, where XX
is your initials.
Location No |
Warehouse |
Location Name |
Location Group |
Location Type |
L1 |
A |
Stored |
30 |
Picking |
General exercise for
Entering Inventory
Location
Required Data
Registering Miscellaneous Demand to Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- For activities in your subproject structure, register miscellaneous demand
for inventory parts.
- Register demand both for items that are to be issued from the project inventory
(not standard planned) and for items that will be issued from standard inventory
(standard planned).
- Save your changes.
General exercise for
Registering Project
Demand
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Release the activities which have connected miscellaneous demand and for
which you want to issue material from inventory.
General exercise for
Executing
Activities
Purchasing Project Miscellaneous Demand
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- For one of your registered miscellaneous demands for inventory parts, create
a purchase requisition.
- Handle this purchase requisition and resulting purchase order.
- Receive the parts into your project inventory, using your inventory location
L1.
General exercise for Purchasing
Project Miscellaneous Demand
Receiving Inventory Parts
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Receive inventory parts into your site's standard inventory, using your
inventory location L1.
General exercise for
Receiving Inventory
Parts
Main Exercise
Purpose: The purpose of these exercises is to show you how
to issue material from both standard and project inventory to your project.
Windows:
Project Navigator/Demand/Misc.Part
Project Navigator/Activity
- Open the Project Navigator
window. Query for your project.
- In the Navigator, select an activity with connected miscellaneous demand
for which you intend to issue from the project inventory.
- Click the Demand tab and then click the Misc. Parts tab.
- Select the desired miscellaneous demand for an inventory part. Check that
the Std Planned Item check box is cleared, so that the items will be
taken from the project inventory.
- You can optionally reserve the items. Right-click and click Reserve
or Reserve manually.
- If reserving manually, the
Manual Reservation
dialog box will appear. On a row with available items, enter the desired quantity
to reserve in the Reserve Qty field. Click OK.
- In the Misc. Parts tab, verify that
the value in the Reserved Quantity field is correct.
- Select the Connections tab. For your
miscellaneous demand object, note that the value in the Committed
column is equal to zero.
Note: It is allowed to issue material that has been acquired via another
activity than the one to which the demand object is connected, but the activity
must be within the same project. In both the
Manual Reservation
and Issue From Inventory
dialog boxes, all available items acquired to one of the project activities will
be shown. The value in the Activity Sequence column shows to which activity
these items were acquired into the project inventory.
- Select your miscellaneous demand, right-click and click Issue
or Issue manually. If issuing manually, the
Issue From Inventory
dialog box will appear.
- In the Quantity Left field, observe the number of items that remains
to be issued.
- On a row with available items, enter the desired quantity to issue in the
Issue Quantity field. Click OK.
- Read the information message that informs you that the parts have been successfully
issued. Click OK.
Note: If you are using an executable that contains IFS/Project
Reporting, the Create
Project Transaction window will appear. Enter a valid report code that
has report code type Material and click OK to create a project transaction
for this issue. You can also choose to create a project transaction for this issue
at a later time. Select the desired miscellaneous demand that you have issued to
your project, right-click and then click Create Project Transaction.
- In the Misc. Parts tab,
verify that the values in the Issued Quantity and Issued Date
fields are correct.
- Select the Connections tab. For your
miscellaneous demand object, note that the values in the Committed and
Used columns are equal to zero. (Used cost is only reported when receiving
into project inventory, not when issuing.)
Note: The progress will not be reported for
the miscellaneous demand line until the related Purchase Order is in the received
status. Once it is in the received state the progress is calculated by dividing
the received quantity by the required quantity and then taking the percentage value
of it.
- Open the Project Navigator
window. Query for your project.
- In the Navigator, select an activity with connected miscellaneous demand
for which you intend to issue from standard inventory.
- Click the Demand tab and then click the Misc. Parts tab.
- Select the desired miscellaneous demand for an inventory part. Check that
the Std Planned Item check box is selected, so that the items will be
taken from standard inventory.
- You can optionally reserve the items, according to steps 5-7 in the above
exercise.
- Select the Connections tab. For your
miscellaneous demand object, note the value in the Committed column.
This value is based on the current part cost for the reserved items.
Note: In both the
Manual Reservation
and Issue From Inventory
dialog boxes, the available quantity in standard inventory will be shown. The value
in the Activity Sequence column will be 0, indicating that the items are
found in standard inventory.
- Issue the items, according to steps 9-13 in the above exercise.
- Select the Connections tab. For your
miscellaneous demand object, note the values in the Committed and
Used columns. The value in the Used column is based on the inventory
transaction value for the issue of this part. The value in the Committed
column has decreased, and reflects the committed cost for the remaining reserved
items.
- Verify that these values update the correct cost elements, based on how
you set up the posting control rule M62 and cost element mappings.
- On the Cost
tab, verify that the values in the Committed and Used columns
have been updated correctly from the connected objects.
Notes:
The progress will not be reported for the miscellaneous demand line until the
related Purchase Order is in the received status. Once it is in the received state
the progress is calculated by dividing the received quantity by the required quantity
and then taking the percentage value of it.
By issuing material, you have created an inventory transaction. When the corresponding
inventory vouchers are updated to IFS/General Ledger, you will be able to retrieve
actual costs.
For an example of an activity where standard material has been issued, you can
refer to the project P101 and the activity 20010.