Using Tasks to Report Progress—Exercises
Basic Data Setup
Progress Templates
Purpose: The purpose of this exercise is to show you how
to create progress templates.
Windows:
Project Navigator/Progress Template
- Create a progress template that can be connected to your tasks.
- Save your changes.
General exercise for Entering
Progress Templates
Required Data
Connecting Tasks to Activities
Purpose: The purpose of this exercise is to familiarize you with the
data that must be in place before you can perform the exercises below.
- Create and connect tasks to activities in your subproject structure.
- Save your changes.
General exercise for Creating
and Connecting Tasks
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the
data that must be in place before you can perform the exercises below.
- Release the activities which have connected tasks.
General exercise for
Executing
Activities
Main Exercise
Purpose: The purpose of these
exercises is to show you how
to report progress on tasks and how to use tasks to update the activity's
progress.
Windows:
Project Navigator/Tasks
Project Navigator/Activity
Project Navigator/Connections
Activity/Tasks
Activity/General
Activity/Connections
- Open the
Project Navigator window. (Alternatively, open the
Activity window.) Query for your project.
- In the Navigator, select the activities that have connected tasks to which
you would like to report progress on. (Alternatively in the
Activity
window, select the desired activities in the Project list.)
Note: Do the following steps to report progress on tasks with no progress
template.
- Click the
Tasks tab. (Alternatively, query for your
activities and do the following steps in the
Tasks
window.)
- For a task that has no value in the Progress Template field, note
that the value in the Progress field is 0%.
- For this task, select the Completed check box.
- Save your changes.
- Observe that the value in the Progress field is 100%.
Note: Do the following steps to report progress on tasks using a progress
template.
- Click the
Tasks tab.
- For a task with a connected progress template, click in the Progress
Template Step field.
- Enter the desired progress template step or select it from the List of
Values.
- Save your changes.
- Observe that the value in the Progress field is equal to the
progress associated with the progress template step that you have entered.
- You can also select the Completed check box for tasks with a
progress template.
- Save your changes.
- Observe that the value in the Progress field is 100%.
- The Task Weighted Progress field will get updated with the
weighted progress of the tasks you have entered.
- Continue in the
Project Navigator window and click the
Activity tab. (Alternatively in the
Activity
window, click the
General tab.)
- In the Progress Method list, click All Connected Objects.
- Save your changes.
- If you have entered planned cost or hours you will notice that the Calculated
Cost Progress and Calculated Hours Progress fields are updated.
This is the activity's weighted progress of all the tasks connected to the
activity. The progress of each task is weighted based on its value for
Planned Hours.
- Note that the Actual Start Date field has a value equal to the
early start date. Observe that the Early Start Date field is no
longer editable.
- Optionally, change the actual start date and save your changes. Note that
the Early Start Date field is changed to be the same date as the
actual start date.
- Click the Connections tab. Observe that the progress for
each connected task is shown here in the Object Cost Progress and
Object Hours Progress fields accordingly.
- When an activity's connected tasks have been performed, and all other work
executed, complete the activity. (For more information about completing
activities, refer to the
Executing
Activities lesson.)
Note: For an example of an activity which uses connected tasks to
report progress, you can
refer to the the project P101 and activity 10010. Assuming that there are
no other connected objects, the activity's calculated progress = (100% *
8/40) + (80% * 16/40) + (30% * 16/40) = 64%.
Activity |
Task |
Completed |
Progress Template |
Progress Template Step |
Object Hours Progress |
Hours Planned |
Activity ID: 10010
Planned Hours = 40
|
Field work |
yes |
|
|
100% |
8 |
Analysis |
|
5 |
40 |
80% |
16 |
Report |
|
5 |
20 |
30% |
16 |