Basic Data Setup
Part Classes
Purpose: The purpose of this exercise is to create some
part classes for the new engineering parts to be created in the next exercise
below.
Windows:
Product Basic Data/Classes
- If you have not already done so, create two new part classes: XX–PP (Project Produced) and XX–PA (Project
Acquired), substituting XX with your name initials.
- Save each record.
General exercise for Product
Basic
Engineering Parts
Purpose: The purpose of this exercise is to create some engineering parts
that will be used as project items in the project product
structure.
Windows:
Engineering Parts
If you have not already done so, create the following new engineering
parts, as shown below, substituting your
initials for XX:
Part Number |
Std Name ID |
Current Revision |
Part Description |
Part Class |
Provide Code |
MPL Part |
20–10XX |
3 |
R01 |
Engine 1600 |
XX–PP |
Make |
Demand |
20-11XX |
3 |
R01 |
Engine Block 1600 |
XX–PA |
Buy |
Demand |
- Save your changes.
General exercise for Establishing
New Part
Required Data
Registering a Delivery Project
Purpose: The purpose of this exercise is to familiarize
you with the data that must be in place before you can do the the exercises
below.
- Register a delivery project at your site.
- Save your changes.
General exercise for Registering a Delivery Project
Main Exercises
Purpose: The purpose of these exercises is to create
a project product structure by adding both the standard planned and
project-specific items.
Windows:
Project Product
Project Product/Items
Delivery Projects
Project Item
Project Item/Consist Of
Project Item/Multilevel
Prerequisite: If you are doing all the exercises in this course,
the exercises below should be performed instead of
the main exercises found in the Copying Product Structures from an Existing
Delivery Project exercise.
- Open the
Project Product window and query
for your project XXPD-01.
- On the
Items tab, create a new record.
- In the Part Number field, enter 20–10XX (Engine 1600) or select it from the List of Values.
- In the Part Revision field, enter R01.
- In the MPL Part list, click Demand.
- Check the value of the Provide Code field. Modify this value, if
required.
- Save your changes.
- Open the Delivery Projects window and query for your project
XXPD-01.
- In the Top Part No field, enter part 20–10XX (Engine 1600) to register the top part.
- In the Top Part Revision field, enter R01.
- Save your changes.
- Open the Project Item window and query for your project
XXPD-01.
- On the
Consist Of tab, create a new record.
- In the Part Number field, enter 20–120 (Cylinder Head 1600).
- Verify that
the part revision is R01.
- Repeat steps 2 and 3 for parts 20–130 (Electric System 1600) and 20–140 (Cooling
System 1600). Note that
these three parts are standard parts.
- Save your changes.
- Click the
Multilevel tab.
- Review
the new project delivery structure.
- To attempt to copy one level of the standard structure into the delivery
project, select part 20–120, right-click and then click Copy Standard
Structure - One Level. Because part 20–120, in this case, has only one
level, only the One Level option is preferable.
- Click
No to the information message regarding copying of phantom parts.
-
You will see a message indicating the parts have been
inserted.
-
Click OK to the warning prompt regarding
insertion of parts.
- Open the
Project Product window and query for your project
XXPD–01.
- On the
Items tab, create a new record.
- In the Part Number field, enter part 20–11XX (Engine Block 1600).
- In the Part Revision field, enter R01.
- In the MPL Part list, click Demand.
- Check the value of the Provide Code field. Modify this value, if
required.
- Save your changes.
- Select the part 20–10XX (Engine 1600) and right-click and then click Project Item to
go to this window.
- Click the
Consist Of
tab.
- Connect the part 20–11XX to the project product structure.
- In the Part No field, enter part 20–11XX and verify that the Project Part
check box is selected.
- Save your changes.
- Click the
Multilevel tab.
- Verify that the following
project product structure exists:
Level |
Part Number |
Part Description |
Number of Children |
Quantity |
+.1 |
20–10XX |
Engine 1600 |
4 |
1 |
+..2 |
20–11XX |
Engine Block 1600 |
0 |
1 |
+..2 |
20–120 |
Cylinder Head 1600 |
3 |
2 |
+..2 |
20–130 |
Electric System 1600 |
0 |
1 |
+..2 |
20–140 |
Cooling System 1600 |
0 |
1 |
+...3 |
20–121 |
Cylinder Head Cover 1600 |
0 |
1 |
+...3 |
20–122 |
Camshaft 1600 |
0 |
2 |
+...3 |
20–123 |
Valve 1600 |
0 |
16 |