Connect Work Order to Project Activity

Explanation

This activity is used to connect a work order to an existing project activity. You will only be able to connect the work orders that do not contain any cost transactions, such as material, tools and facilities, operations and so on.

Prerequisites

System Effects

Window

Prepare Work Order 

Related Window Descriptions

Prepare Work Order
Prepare Work Order/General
Historical Work Orders 
Historical Work Order
Historical Work Order/General

Procedure

  1. Open the Prepare Work Order window, and click the General tab.
  2. Create a new work order (F5), or query for an existing one (F3).
  3. Right-click anywhere on the window, point to Project Connections, and click Connect to Activity. The Connect to Activity dialog box appears.
  4. Enter the program ID, project ID, sub project ID, and the relevant activity sequence. Click List to select the appropriate values.
  5. Click OK. If the work order is successfully connected to a project activity, the Project Connected check box on the General tab will be selected.