Copying from Project Resource Forecast—Exercises
Required Data
Create Project Resource Forecast
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- Create a project resource forecast
General exercise for
Create Project
Resource Forecast
Main Exercise
Purpose: The purpose of this exercise is to copy information
from an existing resource forecast
Windows:
Project Resource Forecast
Copying from Resource Forecast
- Open the Project Resource Forecast window
and query for the project for which you created a resource forecast.
- Right-click in the header and select Create
Resource Forecast.
- Enter Version 2 in the Version Description field.
- Select the Copy From Forecast check box.
- Click Next.
- Select the Copy Hours Spread check box.
- Select the Set ETC check box.
- Click FINISH. A dialog box inquiring whether you wish to view the
resource forecast
will open, click Yes.
- Observe that the values in the ETC Hours have been copied to the
resource forecast from
the previous resource forecast.