Using Document Packages to Report Progress—Exercises
Required Data
Connecting Document Packages to Activities
Purpose: The purpose of this exercise is to familiarize you with the
data that must be in place before you can perform the exercises below.
- Connect document packages to activities in your subproject structure.
- Save your changes.
General exercise for Connecting
Document Packages to Activities
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the
data that must be in place before you can perform the exercises below.
- Release the activities which have connected document
packages.
General exercise for
Executing
Activities
Main Exercise
Purpose: The purpose of these
exercises is to show you how
to report progress to activities using connected document packages.
Windows:
Document Package
Project Navigator/Activity
Project Navigator/Connections
Activity/General
Activity/Connections
- Open the
Document Package window
and populate with one of your document packages.
- For one of the documents in the document package, click in the Document
Milestone No field.
- Enter the desired milestone number or select it from the List of Values.
- Observe that the value in the Cumulative Progress field is equal to the
progress associated with the milestone number.
- Save your changes.
- Observe that the value in the Hours Progress field in the header of the
Document Package
window is calculated. The
progress is weighted based on the planned hours of each connected
document.
- Open the
Project Navigator window and click the
Activity tab. (Alternatively in the
Activity
window, click the
General tab.) Query for your project.
- In the Navigator, select the activities which has
connected document packages on which you have reported progress.
(Alternatively in the Activity window, select the desired
activities in the Project list.)
- In the Progress Method list, click All
Connected Objects.
- Save your changes.
- Observe that the Calculated Cost Progress and Calculated
Hours Progress fields are updated according to the cost and hours you
have specified. In the example it is the Calculated
Hours Progress field that is updated. This is the
activity progress based on the progress of the connected document packages.
- Note that the Actual Start Date field has a value equal to the
early start date. Observe that the Early Start Date field is no
longer editable.
- Optionally, change the actual start date and save your changes. Note that
the Early Start Date field is changed to be the same date as the
actual start date.
- On the
Document Package window, change the progress of one
of your documents.
- Click the
Activity tab again. (Alternatively in the
Activity
window, click the
General tab.)
- Observe that the activity calculated progress is updated, considering your
change.
- Click the Connections tab. Observe that the
hours progress for
each connected document package is shown here in the Object Hours Progress field.
- When an activity's connected document packages have been performed, and
all other work executed, complete the activity. (For more information about
completing activities, refer to the
Executing
Activities lesson.)
Note: For an example of an activity which uses connected document
packages to
report progress, you can
refer to the project P101 and activity 10040. Assuming that there are
no other connected objects, the activity's calculated
hours progress = (60% * 10/15) +
0% = 40%.
Activity |
Document Package |
Documents |
Document Milestone Template |
Document Milestone No |
Object Hours Progress |
Hours Planned |
Activity ID: 10040
|
P101-10 |
P101-1000 |
20 |
20 |
60% |
10 |
P101-1030 |
20 |
|
|
5 |