Updating Planned Costs From the PQL—Exercises
IMPORTANT |
It is extremely important that you set up and work within your own
site to maintain your data integrity. If you work within any other
site, you will compromise your own exercise data as well as the data of
other students. Predictable exercise results require that your data be
isolated in your own site. |
Required Data
Working with RFQ in Project
Purpose: The purpose of this exercise is to familiarize
you with the data that must be in place before you can do the exercises
below.
- Create request for quotations (RFQ) from items in the project quotation
list (PQL). You need two RFQs for the following exercise.
- Handle one of the RFQs by registering supplier quotations. Approve the
quotation and create a supplier blanket for a purchase part or a purchase
order for a no-part.
- For the remaining RFQ, register supplier quotations with different prices
but do not approve the quotation.
General exercise for Working with
Requests for Quotations in Project
Main Exercise
Purpose: The purpose of this exercise is to show you how
retrieve a supplier price to the project quotation list. This supplier price is
based either on the best available supplier price or it is updated automatically
when the blanket or order quotation is approved. Based on the PQL supplier price,
update the miscellaneous demand’s expected supplier price and its planned
cost.
Windows:
Project/Quotation List
Project/Demand/Misc. Parts
Project/Demand/Misc. No Parts
Agreement Quotation
Order Quotation
Updating Miscellaneous
Demand Planned
Cost from the PQL
- Open the
Project window and query for your project.
- Click the Quotation List tab.
- For the PQL items that have a connected RFQ number, note the connected
purchase parts or no-parts.
- Click the
Demand/Misc. Parts tab for purchased parts
or for no-parts click the
Demand/Misc.
No Parts tab.
- Select the project demand
row, right-click and select Cost Elements, to open the
Planned Cost/Hours per Cost
Element dialog.
Note the values for planned costs per cost element.
Note: Do the following steps to retrieve the best available supplier
price to the PQL.
- Click the Quotation List tab again.
- Find the PQL record where the Request for Quotation Approved check box
is not selected. This indicates that the RFQ is not yet approved, and
quotations are still being received from suppliers.
- Select this row, right-click and then click Get Best Supplier Price.
Note the values in the Supplier
Price and Total Price fields. (Note that this function will not
be enabled if the order quotation has already
been approved.)
- For a purchase part, open the
Agreement Quotation window.
Alternatively for a no-part, open the
Order Quotation window.
Query for your RFQ number.
- In the Request No list in the header, select
the different suppliers and note each quotation.
- Verify that the lowest supplier price has been retrieved to the PQL, and that the
total price in the PQL shows this supplier price
multiplied with the quantity.
- Find the PQL record where the Request for Quotation Approved check box
is selected. This indicates that the RFQ is approved.
- Note that the value in the Supplier
Price and Total Price fields are automatically updated base on
the approved supplier price.
Note: Update the miscellaneous demand’s expected supplier price.
Update the planned cost of the miscellaneous demand based on the expected
supplier price.
- Click the Demand/Misc. Parts tab or
Demand/Misc. No Parts tab again.
- Select a PQL record, right-click and click Get Supplier Price.
- Note that the value from the Supplier
Price field in the Quotation List tab for this purchase
part or no-part is retrieved to this tab's Expected Supplier Price
field.
Note: The values are not saved in the Expected Supplier Price
field. It is assumed that you will update the miscellaneous demand's
planned cost immediately if you accept the expected supplier price.
- Right-click and then click Update
Planned Cost.
- A message appears asking if you would like to update the planned cost from
the PQL. Click Yes.
- Select the project demand row, right-click and select
Cost Elements, to open the Planned Cost/Hours per Cost
Element
dialog.
Verify that the values for planned costs have been updated based on the value
in the Expected Supplier Price field.