Lot-Sizing Techniques and Adjustments—Extended Exercises

IMPORTANT
It is extremely important that you set up and work within your own site to maintain your data integrity. If you work within any other site, you will compromise your own exercise data as well as the data of other students. Predictable exercise results require that your data be isolated in your own site.

Basic Data Setup

PMRP Extended Data Setup

Purpose: The purpose of this exercise is to set up the required prerequisite data needed for the extended MRP exercises. You must do this exercise once to support the extended MRP exercises in the current database. (If the database has been refreshed since the time you set up the data for the MRP extended exercises, you will need to set up the data again.)

  1. If you haven't done so already, create your own site and set up the extended MRP data (for extended exercises) in that site. 

General exercise for Overview of Extended MRP Data

Main Exercise

Purpose: The purpose of these exercises is to perform PMRP on the parts that you have already defined and evaluate the result.

Windows:
Perform PMRP
Background Jobs
PMRP Material Plan
PMRP Part Information

Performing PMRP

  1. Open the Perform PMRP window and start the PMRP process on project XX100 in your primary site.
  2. Check the process from the Background Jobs window.
  3. Go to the next section when the process is done.

Evaluating PMRP Result

  1. Open PMRP Material Plan window and query for parts in your primary site.
  2. When the query results display, notice that the 90-210, 90-272, 90-273, and 90-274 parts are not listed because those parts are defined with a planning method of either B (order point planning), C (replenishment level), or N (next level demand), and PMRP does not handle parts with those planning methods.
  3. Select the 90-220 part from the Part Number list. This part is defined with planning method D (fixed lot size) and has a multiple lot size of 5. In the product structure, the quantity per assembly of this part is 2 because there is a customer order demand of 3 pieces for the 90-200 parent part. This demand will require 6 pieces of the 90-220 part. To supply this demand, PMRP will look at the multiple lot size setting and create a plan receipt of 10 pieces.
  4. Select the 90-230 part from the Part Number list. This part is defined with planning method E (least unit cost) and has an ordering cost of 100, inventory interest of 3%, and a material cost of 200. The calculated stock-keeping cost per day will be 200 x 0.03 / 220 = 0.027. 

Note: The calculation above assumes that the number of stock keeping days per year is 220 days, which is the default value specified at installation.

  1. PMRP will look at the demands for 90-230 part as in the table below: 
No Date Demand Qty  Description
1 today+1 month 3 Demand from Customer Order
2 today+1 month 100 Demand from Project Misc. parts
3 today+2 months 100 Demand from Project Misc. parts
4 today+3 months 100 Demand from Project Misc. parts
  1. On the first day, the system will see a demand of 103 pieces from the customer order(s) and the material requisition(s). At this point PMRP will first determine whether it should create supply for future demand so it can obtain least unit cost. As calculated, there are 32 days between demand numbers 2 and 3, and 33 days between demands numbers 3 and 4. After comparing setup costs against stock-keeping costs, PMRP determines that it would be best to create supply only for the future demands of demand numbers 2 and 3, so a shop order requisition for 203 pieces is created. This shop order requisition will supply the demand number 1 (3 pieces), demand number 2 (100 pieces), and demand number 3 (100 pieces). Demand number 4 exists 3 months ahead and will be supplied later because it will increase inventory cost too much.

Note: You may find that your exact results differ from what is described above because the number of days between each demand affects the inventory cost. 

  1. Select the 90-231 part from the Part Number list. This part is defined with a maximum lot size of 10 pieces. Demand from the parent part is 203 pieces and the supply cannot be ordered as one requisition because that would exceed the maximum lot size. Instead PMRP will break up the order into twenty requisitions for 10 pieces each and one requisition for 3 pieces. The same situation occurs with demand number 2, which is for 100 pieces. PMRP will supply that demand by creating ten requisition with 10 pieces each.
  2. Select the 90-240 part from the Part Number list. This part is defined with planning method F ( Part Period Balancing), and has an ordering cost of 100, inventory interest of 0.5%, and a material cost of 200. The calculated stock-keeping cost per day will be  200 x 0.005 / 220 = 1/220. This will obtain the optimal quotient:  100 /(1/ 220) = 22000. 

Note: The calculation above assumes that number of stockkeeping days per year is 220 days which is the default value specified at installation.

  1. Then PMRP will look at the demands for 90-240 part as in the table below 
No Date Demand Qty  Description
1 today+1 month 6 Demand from Customer Order
2 today+1 month 100 Demand from Project Misc. parts
3 today+2 months 100 Demand from Project Misc. parts
4 today+3 months 100 Demand from Project Misc. parts
  1. When demand number 1 for 6 pieces is processed, PMRP will first determine whether it needs to create supply for future demand to find the optimal relationship between order overhead and stock-keeping costs using the optimum quotient. PMRP determines that it is best to supply the future demands of numbers 2, 3, and 4 along with the demand of number 1. Therefore as calculated, PMRP creates supply for 306 pieces on the demand number 1 date.

Note: You may find that your exact results differ from what is described above because the number of days between each demand affects the inventory cost. 

  1. Select the 90-250 part from the Part Number list. This part is defined with planning method G (order cover time) and has the order cover time set to 5 days. With this setting, when PMRP finds the first demand it also will look to supply any other demand 5 days ahead. The first shop order requisition for this part is created with a quantity of 56 pieces. This supplies the first demand of 6 pieces and the material requisition of 50 pieces. The third demand for 5 pieces is supplied separately because it is outside the order cover time. 
No Date Demand Qty  Description
1 today+1 month 6 Demand from Customer Order
2 today+1 month + 3 days  50 Demand from Material Requisition
3 today+2 months  5 Demand from Material Requisition
  1. Select the 90-251 part from the Part Number list. The part has a Manufactured Supply Type of Schedule, which means this part is not handled by PMRP.
  2. Select the 90-260 part from the Part Number list. This part is defined with planning method K (blow through), which means that when MRP finds any demands for this part, it will not create supply for them. Instead it will pass demand to its components. Check the created demands for 90-261 part, which is a component part. 
  3. Select the 90-270 part from the Part Number list. This part is defined with planning method M (manufacturing cell), which means that MRP will create a requisition to supply demands but it will not break down the demand for its components. Part 90-271, component of 900-270, is not listed in this screen as there are no transaction for it.
  4. Select the 90-280 part from the Part Number list. This part is defined with planning method P (phantom), which means that the net requirements will be passed to its components but no supply will be created for this part. As this part has stock on hand of 1 pcs, demand of 3 pcs which is from its parent 90-200 customer order will be reduced to 2 pcs, then passed to component 90-281.