Initial Exercises—Dynamic Order Processing 2
Basic Data Setup
Purpose: You need to do this exercise only once
to support all Make to Order exercises in the current database. If you are
participating in instructor led courses, you will not set up this specified data
until after the following initial exercises. If you are doing self-directed
learning and want to complete the following initial exercises, you should first
complete this linked exercise. The purpose of this exercise is to simplify the
process of setting up data correctly in order to complete the exercises below.
It includes setting up your own site and copying specified data to that site.
Overview
of Make To Order Data lesson
Initial Exercises
Purpose: The purpose of these initial exercises is for
the instructor to use them to demonstrate the basic functionality in Dynamic
Order Processing. These exercises are divided into two exercise documents which
should be completed sequentially before going on to the various key exercises.
This second portion includes:
-
Resolving DOP Alarms
-
Calculating DOP Costs
-
Comparing DOP Structures
-
Analysis of DOP Orders
IMPORTANT |
These initial exercises are intended for
instructor use.
If you are a student, it is extremely important
that you set up and work within your own site to maintain your
data integrity. If you work within any other site, you will
compromise your own exercise data as well as the data of other
students. Predictable exercise results require that your data
be isolated in your own site. |
Purpose: The purpose of this exercise is to introduce
you to the basic functionality for resolving quantity alarms. The
system can be set to generate alarms that will indicate if the supply is for a smaller quantity than is required for the DOP order.
Prerequisites: To demonstrate this functionality, you must have existing DOP orders with supply that is not available in sufficient quantity.
In this exercise, we will demonstrate a scenario
involving insufficient quantity.
Windows:
DOP Order
Generate DOP Alarm
DOP Header/Tree Structure
DOP Order/Tree Structure
Steps: To complete this exercise, perform the following
steps.
Assume that the shop order has been changed by someone on the
shop floor. You will make changes in the system to reflect this. We will use
this shortage to generate an alarm to resolve.
- In the
DOP Order/Supply/Shop Order tab, right-click and then
click Shop Order Detail. This will open the
Shop Order window.
- In the Lot Size field, change the quantity from 3 to 2. Save your
changes. Click Yes in the dialog box asking if you want to re-plan.
- In the
DOP Order window, right-click and then click Specific
Order Alarm Generation.
- This will create the alarm record, which can be viewed in the
Alarms
tab. You may need to re-query the record. The source of the alarm is shop
order, it is a quantity alarm with a shortage of 1. (You can also see that
the Alarm Exists check box is selected in the
Details
tab.)
- Optionally, you can acknowledge that you have seen this alarm, by
right-clicking and then clicking Acknowledge. This status can
be used later in queries.
- There are two ways to resolve the shortage in this window, using the right
mouse button options, either by netting or increasing the quantity on the
shop order. Select the alarm record, and right-click and then click Increase
Quantity.
Note: You will not be able to do this if the shop order
has been started.
- To view the changes in the shop order, right-click and then click Go to
Source. Note that the lot size is now 3.
-
Return to the
DOP Order window, and run the
alarm generation again (right-click and then click Specific Order Alarm
Generation). You may need to re-query the record to see that the alarm
has been resolved and the alarm record has been removed.
- Another way to resolve a quantity alarm is to create a new pegged
order. On the
DOP Order/Detail tab or the
DOP
Header/Structure tab, right-click and then click Create Pegged Order to create another pegged order for the additional
amount required.
Purpose: The purpose of this exercise is to introduce
you to the basic functionality for resolving date alarms. The
system can be set to generate alarms that will indicate if the supply is due
later than is required for the DOP order.
Prerequisites: To demonstrate this functionality, you must have existing DOP orders with supply that is not available
by the required date.
In this exercise, we will demonstrate a scenario based on a late shop order.
Windows:
DOP Order
Generate DOP Alarm
DOP Header/Tree Structure
DOP Order/Tree Structure
Assume that due to limited shop floor capacity, the supplying
shop order need date has been changed. You will make changes in the system to reflect this. We will use
this simulated delay to generate an alarm to resolve.
-
Using the same DOP order from above, note the date in the Revised
Due Date field in the
Details tab:___________.
-
Click the Supply/Summary tab. Select the
record for shop order supply type. Click and then right-click Go to Supply.
This will open the associated shop order.
-
In the
Shop Order window, add seven days to the
date in the Need Date field, and save the record. Click Yes in
the dialog box to replan the DOP order.
-
In the
DOP Order window, right-click and then
click Specific Order Alarm Generation. This will create the alarm,
which you can view in the
Alarms tab. You may need to re-query
the record. The source of the alarm is shop order, it is a time alarm with a
delay of 7. (You can also see that the Alarm Exists check box is
selected in the
Details tab.)
-
Optionally, you can acknowledge that you have seen this
alarm, by right-clicking and then clicking Acknowledge. This
status can be used later in queries.
-
There are two ways to resolve the delay in this window,
using the right mouse button options. To automatically change the need date
in the shop order, select the alarm record, and right-click and then click Adjust
Date. Right-click and then click Go to Source to open the shop
order. Select the Schedule Shop Order right mouse button option. This
will change the start and finish dates.
-
Alternatively, you can manually adjust the need date in the
shop order by right-clicking and then clicking Go to Source, and
then clicking Yes in the dialog box asking if you want to re-plan.
-
Return to the
DOP Order window, and run the
alarm generation again (right-click and then click Specific Order Alarm
Generation). You may need to re-query the record to see that the alarm
has been resolved and the alarm record has been removed.
Purpose: The purpose of this exercise is to introduce
you to the basic functionality for calculating costs for all sites, per site, or DOP ID for standard, estimated, and/or actual costs.
You will also see how to view cost variances.
Prerequisites: To demonstrate this functionality, you must have existing DOP orders
which are released to create shop orders. You also need to have reported
time or quantity or reported scrap on these shop orders. In this exercise, we will demonstrate
how to view the costs for a DOP ID.
Windows:
Calculate DOP Cost
DOP Header/Costing
DOP Order/Costing
- In the DOP Header window, query for your DOP ID which
has been released and whose pegged shop orders have some quantity or time
reported.
- In the
Costing tab, right-click and then click Calculate DOP
Cost to open the Calculate DOP Cost dialog window.
- The DOP ID field will default with your DOP ID value.
- Select the Standard, Estimated, and Actual check
boxes, and then click OK.
- Note that this is a background process and it may take a few moments to
complete.
- Re-query your DOP ID to view the results in the
DOP Costing
tab.
- Note that this process can also be started from the
Calculate DOP Cost
window.
- You can choose to schedule this as a job which will run at specified times
on specified days.
- You can choose to run the process for all sites, a specified site, or a
specified DOP ID.
Purpose: The purpose of this exercise is to introduce
you to the basic functionality for comparing DOP structures with each other and
with the standard Bill of Material (BOM). Using an existing DOP record, you will
modify the structure by selecting a structure alternative. This will allow you
to compare this alternative structure with both the standard bill of material
and the DOP structure created in the Creating DOP Structures lesson above.
Prerequisites: You will use the second customer order
line you created in the first exercise above. Structures and routings for the specified
part(s) in the DOP header must already exist.
Windows:
Customer Orders
Compare DOP Order and BOM
Comparing DOP Structures
Monitoring Cost Performance
- In the
Customer Order window, query for the order you
created in the first exercise above.
- Click the DOP Info tab. In the Line No list, click the record for delivery number 2 (Del No 2).
- In the table area, select the line and right-click and then click DOP Header
Detail to open the associated DOP header record.
- In the DOP Header window, click in the header area
or the
Detail tab, and right-click and then click Create DOP Structure,
and then click Create DOP Structure.
- In the Create DOP Structure/Routing window, click in the Structure Alternative No field,
click List to select
alternative structure 1, and then click OK.
Note: You do not need to net or release the DOP header to
be able to make the following comparisons.
- Open the
Compare DOP Order and BOM window and populate or query for
your DOP ID. If necessary, select your DOP ID from the list in the DOP ID
field.
- In the Part No field, select 22-110 to compare your DOP structure to the standard bill of material for the part.
- Click All, Equal, and Difference to view,
respectively:
- The entire structures of both the DOP and the BOM.
- The parts of the structures that are the same,
- The parts of the structures that are different.
- Click Tree after clicking each of the above choices to compare the
structures in a graphical view.
- Open the Comparing DOP Structures window. Populate or query
for your two DOP IDs.
- In the Comparator section, click one of your DOP IDs from the DOP ID list. Select the other DOP ID in the DOP ID field
of the Comparatee section.
- Click All, Equal, and Difference to view,
respectively:
- The entire structures of both DOP IDs.
- The parts of the structures that are the same.
- The parts of the structures that are different.
Purpose: The purpose of this exercise is to introduce
you to the basic functionality for viewing a cost
performance graph of a DOP structure.
Prerequisites: You must have run the DOP cost
calculation process for a DOP ID that has been released with at least one pegged
shop order having time or quantities reported.
Windows:
Monitoring Cost Performance
DOP Header/Performance Monitoring
- In the
Monitoring Cost Performance window, query for the DOP
ID from the Calculating DOP Costs exercise above.
- By referring to the Legend in the graph area, you can see different performance, cost,
and value graphs for this DOP ID.
- Note that you can also view this information in the
DOP
Header/Performance Monitoring tab.
- To generate
information and create visual presentations, right-click and then click the following options: Calculate DOP Cost,
Copy, Print, Save Graph As, and Reset To Default.