Create Analysis for Production Schedule Part
Explanation
Use this activity to create one or more analyses connected to a production schedule.
You may want to create more than one analysis to fulfill a particular
sample frequency. For example, if you are producing the parts over a five
hour period and want to have a sample frequency of once per hour, you
can create five analyses.
The routing operation number determines whether a
specific data point will be included in the created analysis. The routing operation
number is defined in Manufacturing Standards/Routings.
Prerequisites
This activity requires a connection between an analysis type and one or more objects on
the production schedule. An
active Control Plan Manufacturing must
exist for the part to be manufactured. The Control Plan is created in
IFS/Quality Management.
System Effects
As a result of this activity, the system transfers the information specified in the dialog box to
IFS/Quality Management, where you can process it further by entering the analysis results.
Window
Production Schedule by
Line
Production
Schedule
by Line Part
Production
Receipt
Report
Point Receipt
Related Window Descriptions
Production Schedule by Line
Production Schedule by Line Part
Production Receipt
Report Point Receipt
Create Analysis
Production Schedule
Production
Schedule Analysis
Analysis
Analysis Result
Procedure
- Query or populate the window.
- In the Production Line list box, select the production line for which you want
to create one or more analyses.
- In the
Production Schedule by Line and
Production
Schedule by Line Part windows, select Create Analysis from the right mouse button menu for the
schedule for which you want to create an analysis. In the
Production Receipt
and
Report Point Receipt windows, select Create Analysis
from the right mouse button menu in the header of the window.
- In the
Production Schedule by Line and
Production
Schedule by Line Part windows, select a Part Revision and Routing Revision using the List
of Values.
In the
Production Receipt and
Report Point Receipt
windows, these fields are filled in by the system. These
fields are required.
- Routing Type, Routing Alternate, and Control Plan Details are filled in by
the system.
- Select one or more routing operation numbers by selecting the check box adjacent to the
Routing Operation
No field for which you would like to create an analysis. Only the
routing operation numbers connected to your Control Plan Manufacturing for the specific
routings will be displayed. This field is required.
- Select the number of analyses you wish to create in the No of Analysis field.
- If desired, select the Print Test Instruction check box to print a test
instruction.
- Click OK. The system now creates one or more analyses of receipts over time for the
selected production lines.
- You will be asked if you would like to view the created analysis overview.
If you click Yes, the Production Schedule Analysis
window appears.
- For more information on entering results, see Enter
Results for Production Schedule Parts.