Schedule Shop Order(s)
Explanation
This activity is used to calculate the start and finish date of the operations
and the shop order, according to the schedule direction.
Efficiency, utilization, maximum hours of operations as well as queue time, transport time
and so on have been taken into account when
scheduling the shop order. If the corresponding site is CBS server enabled, then it will be used to schedule the shop order.
Prerequisites
N/A
System Effects
As a result of this activity:
- The shop order(s) will be (re)scheduled with the new
start and finish dates based on the infinite scheduling or the CBS server
logic. If Schedule Direction is
set to Forward Scheduling
the order will be scheduled from its
Earliest Start Date
and forward. If Schedule
Direction is set to
Backwards Scheduling
the order will be scheduled backwards from its
Need Date.
- Manual scheduling changes done
to the operations of the order will be overwritten.
- Operation scheduling done by
IFS/Advanced Planning
Board will be
overwritten.
Window
Shop Order
Shop Orders
Disposition
Shop Order
Related Window Description
Schedule Shop Order(s)
Shop Order
Shop Orders
Disposition Shop Order
Select Visualization
Related Visualization Chart Descriptions
Machine Load Summary
Machine Load In Standard Hours
Machine Operation Load In Standard Hours
Machine Load
Shop Order Machine Load
Shop Order Labor Load
Shop Orders Material Availability
Shop Orders Material Availability Summary
Procedure
To schedule shop orders using the
data view from
Shop Order
or Disposition Shop Order window:
- Open the
Shop Order
or Disposition Shop Order window and search for the
order to schedule.
- Right-click and then click Schedule Shop Order.
To schedule shop orders using the
data view from
Shop Orders window:
- Open the
Shop Orders
windowand search for the order(s) to schedule.
- Right-click and then click Schedule Shop Order.
- Select Schedule Using Existing Shop Order
Settings if you want to base the scheduling on the existing Schedule
Direction, Earliest Start Date and Need Date of the shop
order(s).
- Select Forward Schedule From Earliest Start
Date and specify an earliest start date if you want to change
Schedule Direction to Forward Scheduling and schedule the shop
order(s) from this date.
- Click OK.
To schedule shop orders using the
visualization view:
- Open a visualizer enabled window
and query for your site.
- If the Data View is displayed, click Visualization View on the title bar.
- Right-click and click Select Visualization.
The Select Visualization dialog box is
opened.
- Double-click Machine Load Summary, Machine Load In Standard Hours,
Machine Load, Shop Order Machine Load, Shop Order Labor Load, Shop Orders Material
Availability Summary or Shop Orders Material Availability.
- Select the bar/segment
representing the shop order(s) you want to schedule. Right-click and select
Schedule Shop Orders. The Schedule Shop
Order(s) dialog box is opened.
- Select Schedule Using Existing Shop Order
Settings if you want to base the scheduling on the existing Schedule
Direction, Earliest Start Date and Need Date of the shop
order(s).
- Select Forward Schedule From Earliest Start
Date and specify an earliest start date if you want to change
Schedule Direction to Forward Scheduling and schedule the shop
order(s) from this date.
- Click OK.