This activity is used to verify required dates for material and requisitions on a work order. When you have specified planned start and completion dates on a work order, the required dates for material issues are determined consequently. If you enter a new material item now, the planned start date is automatically suggested as the required date for the material. You can still remove or change the date. Before you carry on and release the work order, you should verify that the required dates for material and requisitions are not later than the planned start date.
Before the information is verified, the following must have been completed:
As a result of this activity, the required dates for material and requisitions are verified.
Use the following procedure to verify the information on the work order: