Reset Status of Purchase Requisition Header or Line to Planned

Explanation

This activity is used to change the status of a released purchase requisition or a requisition line to Planned.

Prerequisites

The purchase requisition or requisition line must have Released status.

System Effects

As a result of this activity, the purchase requisition or requisition line is demoted from Released to Planned status.

Window

Prepare Work Order

Related Window Descriptions

Prepare Work Order
Prepare Work Order/Requisitions
Prepare Work Order/Requisitions/Part Requisition Lines
Prepare Work Order/Requisitions/No Part Requisition Lines
Prepare Work Order/Requisitions/Rental Part Requisition Lines

Procedure

Use the following procedure to demote a requisition line to Planned:

  1. Open the Prepare Work Order window and query for the applicable work order number.
  2. Click the Requisitions tab and query for the applicable purchase requisition number.
  3. Click the Part Requisition Lines, No-Part Requisition Lines or the Rental Part Requisition Lines tab and select the requisition line to be demoted. If required, you can also select several lines.
  4. Right-click and then click Change to Planned. The status of the line is changed back to Planned.

Use the following procedure to demote an entire requisition to Planned:

  1. Click in the header of the Requisitions tab.
  2. Right-click and then click Change to Planned. The status of the header and all lines is changed to Planned.