Replan and Reschedule Activities

Explanation

Use this activity to replan and reschedule the activities (i.e., operation tool-and-facility lines) that have allocations.

Prerequisites

Resources must be allocated to activities in the respective windows.

System Effects

As a result of this activity, the operation and/or tool-and-facility line will be replanned and rescheduled.

Window

Resource Allocation Gantt

Related Window Descriptions

Resource Allocation Gantt

Procedure

  1. Open the Resource Allocation Gantt window and perform a search.
  2. Filter the results using the fields in the Filters area if required.
  3. To move the allocations, select the horizontal bar, drag and drop to the required time slot.
  4. To change the duration of the allocation, resize the bar or double-click on the bar and enter new start and end dates and times.
  5. Save the information (F12).