Use this activity to define the search criteria to view information on the Resource Load Graph window and the Resource Allocation Gantt window.
- For WO operation lines, values should be entered in the Executed By, Planned Start, Planned Finish and Allocated Hours fields (applicable for both single and multiple allocations).
- For PM operation lines the PM_PLAN_OPERATION parameter should be set to TRUE (IFS/Application Services), and for each line in the PM plan, the Executed By, Planned Start, Planned Finish and Planned Hours fields for the relevant operations should contain values. Additionally the PM action should be active.
- For WO tool-and-facility lines, the From Date/Time and To Date/Time fields should contain values.
As a result of this activity, information will be displayed on the Resource Load Graph window or the Resource Allocation Gantt window.
Resource Load Graph
Resource Allocation Gantt
Resource Load Graph
Resource Allocation Gantt
Search Resource
To search for work orders and PM actions: