Define Predecessor Relationship for Work Order

Explanation

This activity is used to define dependencies between work orders within a particular work order structure. The relationships defined would be useful when rescheduling work orders.

Prerequisites

To perform this activity, work orders must be included in a work order structure.

System Effects

As a result of this activity, work orders will be connected to each other in a Predecessor - Successor (Parent - Child) relationship than can be used during scheduling.

Window

Prepare Work Order

Related Window Descriptions

Prepare Work Order
Prepare Work Order/General
Predecessors 

Procedure

  1. Open the Prepare Work Order window.
  2. Populate (F2) or query (F3) for the necessary work order.
  3. Click the General tab.
  4. Right-click and then click Predecessors. The Predecessors dialog box opens.
  5. Select the check box against the work order that should act as the predecessor.
  6. Click Save and Close.