Setting Up Scheduled Tasks for Transferring Data—Exercises

Main Exercise

Purpose: The purpose of this lesson is to show you how to set up the scheduling task which will be used to transfer data to 360 Scheduling.

Windows:
New Database Task Schedule

Set up a Scheduled Task for Transferring Data to 360 Scheduling

  1. Open the New Database Task Schedule window and create a new record (F5).
  2. In the Schedule Name field, enter a name for the scheduled task.
  3. In the Task Name field, use the List of Values to select the correct schedule method (method description Send Data For Schedule, method name SCH360_SEND_DATA_UTIL_API.SEND_DATA_FOR_SCHEDULE, module SCH360 and LU Sch360SendDataUtil)
  4. To define when the scheduled task should be performed, click one of the options under Schedule and enter the time in the Time field.
  5. Enter values for the parameters under Parameters.
  6. Enter the language and start and stop dates under Advanced.
  7. To activate the scheduled task, select the Active check box.
  8. Save the record (F12).