Completing Sub Contract—Key Exercises

Required Data

Activating Sub Contract

Purpose: The purpose of this exercise is to show you the required data that is used in the exercises below.

  1. Activate the sub contract.

General exercise for Activating Sub Contract

Main Exercise

Purpose: The main purpose of this exercise is to show you how to complete a sub contract.

Windows:
Sub Contract
Sub Contracts

Completing Sub Contract

  1. Open the Sub Contract window.
  2. Populate (F2) or query (F3) for the necessary sub contract.
  3. Right-click the header of the window, point to Status and then click Complete.
  4. A message requiring approval of the step appears, click Yes.
  5. Verify that the sub contract is in the Completed status.