Purpose: The purpose of this lesson is to learn how to create material demands for a maintenance order before it is released. You will learn how to view, add, remove, reserve, unreserve, peg and unpeg material demands for a maintenance order. You will also learn how to re-initiate material demands for a maintenance order.
Prerequisites: Verify that the following prerequisites are fulfilled:
The maintenance order is set to the Under Preparation status and valid predefined operations (instructions or subtasks) are retrieved for the assigned tasks.
If tasks exist without operations or if additional operations are required, connect the valid operations to the assigned tasks.
Ensure that material requirements exist for these operations (instructions or subtasks).
Purpose: The purpose of this exercise is to learn how to view the material required for a maintenance order.
Windows:
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic/Material Required
Purpose: Once the scope of the maintenance visit is defined, material demands can be created for the maintenance order before a work order is generated for the visit. The purpose of this exercise is to learn how to release the material demand for the maintenance order. As a result, a material demand is created for each material requirement in the scope.
Prerequisites: The maintenance order must be in the Under Preparation status and have valid material requirements (in the Material Required sub tab). The Material Demand Released check box should not be selected.
Windows:
Maintenance Order
- Inventory Part Availability Planning/Detailed Planning
- Inventory Part Availability Planning/Procurement Planning
Purpose: The purpose of this exercise is to learn how to manually reserve material demands for a maintenance order. When manually reserving demands it is you and not the system that will determine how many parts should be reserved for the maintenance order. Note that you cannot reserve more parts than what is required on the particular order line.
Prerequisites: The maintenance order must be in the Under Preparation status and have valid material requirements (in the Material Required sub tab). Verify that the Material Demand Released check box is selected for the maintenance order.
Windows:
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic/Material Required
Purpose: The purpose of this exercise is to learn how to unreserve material demands for a maintenance order. If you have reserved a part for a maintenance order, you can remove that reservation prior to releasing the maintenance order by manually entering the quantity to unreserve.
Prerequisites: The maintenance order must be in the Under Preparation status and have valid material requirements (in the Material Required sub tab). Material reservations must exist. Verify that the Material Demand Released check box is selected for the maintenance order.
Windows:
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic/Material Required
Purpose: The purpose of this exercise is to learn how to peg material demands to an existing supply. You can view which lines are available and then decide which of them should be connected. The purpose behind this connection is to automatically allocate supplies to the pegged demand when the supplies are received.
Prerequisites: The maintenance order must be in the Under Preparation status and have valid material requirements (in the Material Required sub tab). Verify that the Material Demand Released check box is selected for the maintenance order.
Windows:
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic/Material Required
Pegged Maintenance Order Material Lines
Purpose: The purpose of this exercise is to learn how to remove pegged material demands by un-pegging them from the existing supply.
Prerequisites: The maintenance order must be in the Under Preparation status and have valid material requirements (in the Material Required sub tab). Pegged materials must exist. Verify that the Material Demand Released check box is selected for the maintenance order.
Windows:
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic/Material Required
Pegged Maintenance Order Material Lines
Purpose: The purpose of this exercise is to learn how to re-initiate material demands for a maintenance order. This is usually done when the material requirement scope of the maintenance order has changed.
Prerequisites: The tasks on the maintenance order must be in the Under Preparation status. Verify that the Material Demand Released check box is selected for the maintenance order.
Windows:
Maintenance Order/Maint. Order Str.
Maintenance Order/Maint. Order Str../Task Details
Maintenance Order/Included Tasks