Generating Execution Logic Structure—Exercises
Main Exercise
Purpose: The purpose of this lesson
is to set a maintenance order with the Execution Logic Structure
distribution type to the Under Preparation status in order to
generate the Execution Logic Structure (ELS) for this maintenance order. The
generated ELS can then be viewed in a graphical object structure and Gantt
chart. You will also learn how to view requirements for material, resources and
tools-and-facilities for the generated ELS.
Windows:
Maintenance Order/Exec. Logic
Maintenance Order/Exec. Logic/Exec. Logic Structure
Maintenance Order/Exec. Logic/Gantt
Maintenance Order/Maint. Order Str./Demand Roll Up
- Open the Maintenance Order window and query (F3) for your
maintenance order.
- Right-click, point to Status and then click
Under Preparation.
- Open the Maintenance Order window and query (F3) for your
maintenance order.
- Click the Exec.
Logic tab.
- In the graphical object
structure, observe the structure of the generated ELS. To view the entire
structure, right-click on the top node (maintenance order) and then click
Expand Descendants.
-
View detailed information on the ELOs and operations
in the adjoining tabs.
- Click the Gantt tab to obtain a graphical view of the ELS.
- Open the Maintenance Order window and query (F3) for your
maintenance order.
- Click the Exec.
Logic tab.
-
In
the graphical object structure, select the structure level in the ELS for
which you want to view material requirements and/or the rolled up requirements
for resources and tools-and-facilities.
- Click the Material Required tab to view requirements
for material for the indicated level.
- Click the
Demand Roll Up sub tab and select a valid period type, i.e., Date,
Week or Month.
- The requirements for resources
and tool-and-facilities can be viewed in the Resources and
Tools and Facilities sub tabs respectively.