Assigning Additional Tasks to a Maintenance Order—Exercises

Main Exercise

Purpose: The purpose of this lesson is to learn how to assign additional tasks to a maintenance order which has been released and for which work orders have been generated.

Windows:
Maintenance Order

Assign Additional Tasks to Maintenance Order