Serialized Production - Exercises
Basic Data Setup
Create Inventory Parts
Purpose: The purpose of this exercise is to show you how to
create
inventory parts to be used by a production line,
Windows:
Inventory Part
- Open the
Inventory
Part window.
- Create new inventory parts for your site and, and enter the values shown
in the table below.
Field
|
Part No |
Part No |
Part No |
Inventory Part
|
61910 |
61911 |
61998 |
Part Description
|
Aluminum Rim 1 |
Aluminum Rim 2 |
Aluminum work piece |
Part Type |
Manufactured |
Manufactured |
Purchased |
Planner |
* |
* |
* |
U/M |
PCS |
PCS |
PCS |
Supply Type |
Schedule |
Schedule |
Order |
Estimated material cost |
|
|
150 (see the
Costs tab) |
2. Save the records.
Part Catalog
Purpose: The purpose of this exercise is to show you how to
define the
parts as serialized.
Windows:
Part
- Open the Part window.
- Query for the parts beginning with 61, and give those parts the
following characteristics shown in the table below.
Field |
Part No 61910 |
Part No 61911 |
Part No 61998 |
Inventory Serial Tracking |
Check |
Check |
Check |
After Delivery Serial Tracking |
Check |
Check |
Check |
Serial Rule |
Manual |
Manual |
Automatic |
Create a Routing
Purpose: The purpose of this exercise is to show you how to
create work
centers to create a routing
Windows:
Routing
- Open the
Routing window.
- Create a routing where Part 61910 has two operations: one with Work
Center 910 (Operation 10), and one with Work Center 920 (Operation 20).
- Make the routing Buildable.
- Create a routing where Part 61911 has two operations: one with Work
Center 910 (Operation 10), and one with Work Center 920 (Operation 20).
- Make the routing Buildable.
Create a Product Structure
Purpose: The purpose of this exercise is to show you how to
create work
centers to create a product structure.
Windows:
Product Structure
- Open the
Product Structure window.
- Create a product structure where Part 61910 contains one piece of
Part 61999.
- Connect Part 61999 to Operation 10.
- Make the structure buildable.
- Create a product structure where Part 61911 contains one piece
of Part 61998.
- Connect Part 61998 to Operation 10.
- Make the structure buildable.
Cost Calculation
Purpose: The purpose of this exercise is to show you how to
create
inventory value for the parts so that production receipt can be performed in
later exercises.
Windows:
All Levels Part Cost Calculation
Copy Cost To Cost Set One
- Open the All Levels Part Cost Calculation window.
- Enter your site, Part 61910, and Cost Set 2.
- Click OK to perform cost calculation.
- Open Copy Cost Set to Cost Set One window
- Enter your site, specify From Cost Set 2 and Part 61910. Select the
Include
Components check box.
- Click OK to perform copying process.
- Open All Levels Part Cost Calculation window again.
- Enter your site, Part 61911, and Cost Set 2.
- Click OK to perform cost calculation.
- Open Copy Cost Set to Cost Set One window.
- Enter your site, specify From Cost Set 2 and Part 61911, and select the
Include
Components check box.
- Click OK to perform copying process.
Connect Part to a Production Line
Purpose: The purpose of this exercise is to show you how to
create or add a
part that can use report points when reporting production.
Windows:
Production Line
- Open the
Production Line window.
- Query for Production Line 900, Production Line for Rims.
- Click the
Part tab. Add Parts 61910 and 61911.
Receive Part into Inventory
Purpose: The purpose of this exercise is to show you how to
receive some
serialized material into inventory
Windows:
Receive Inventory Line
- Open the
Receive
Inventory Part window. Query for the part 61-998.
- Receive 50 pcs of Part 61998 into Location RLI.
Main Exercise
Purpose: The purpose of this lesson is to show you how
serialized production works with production schedules.
Windows:
Production Schedule by Line
Issue Inventory Part
Serialized Production
- Open the
Production Schedule by Line window.
- Create a new schedule for Part 61910. Remember that this is serialized
production, so you should not include too many pieces in each schedule.
- Select a schedule line for 61-910. Right-click and then click Production Receipt.
- In the
Production Receipt window, Enter 10pcs for Qty
reported. Select the Report
Point check box. Specify immediate backflush and select Report Point
from List. Click OK.
- Go back to
Production Schedule by Line window. Right-click and then click Production Receipt.
- Enter 10pcs for Qty reported.
Select the Complete check box. Specify immediate backflush and
select Location No from List. Click OK to perform Production
Receipt.
- Specify the serial numbers and click OK.
- Open the Issue Inventory Part window, and check the results.
Multi level Serialized Production
- Open the
Production Schedule by Line window.
- Query for Production Line 900, Production Line for Rims
- Create a new schedule for Part 61911. Remember that this is serialized
production, so you should not include too many pieces in each schedule.
- Select a schedule line for 61-910. Right-click and then click Production Receipt.
- n the
Production Receipt window, Enter 10pcs for Qty
reported. Select the Report
Point check box. Specify immediate backflush and select Report Point
from List.
- Click Components to open
Production Receipt Material
window. Click Assign to open
Production Receipt Reservation
window.
- Click Create to open
Inventory Part Location window.
Select the required number of parts with serial numbers and click OK.
- Click OK twice to accept the reservation.
- Go back to
Production Schedule by Line window. Right-click and then click Production Receipt.
- Enter 10pcs for Qty reported.
Select the Complete check box. Specify immediate backflush and
select Location No from List. Click OK to open
Production
Receipt Serials window.
- Click Create Interval to open Enter Sequence/Serial
window.
- Create an interval, and then click OK.
- Click OK again to accept the serials created.
- Open the Issue Inventory Part window, and check the results.