Reverse Production Receipt - Exercises
Basic Data Setup
The purpose of this exercise is to show you how to show you how to set up the
basic data that will be used in the exercises below.
General exercise for Report Production
General exercise for Define a
Production Line with Report Points
Required Data
Create Production Schedule
Purpose: The purpose of this exercise is to show you how to
create a production schedule that needed for
reverse production receipt exercise.
Windows:
Production Schedule by Line
- Open the
Production Schedule by Line window. and query for Production Line 900,
Production Line for Rims.
- You should have several schedules that were created in previous exercises.
If not, create a schedule for Part 61–901.
Main Exercises
Purpose: The purpose of this lesson is to demonstrate
the functionality for reversing production.
Windows:
Inventory Part Currently On Hand
Production Schedule by Line
Production Receipts
Reverse Production Receipt—Report Point
- Open window Inventory Part Currently On Hand
- Query for the Part 61-999
- Make a note of the quantity on hand for part 61-999
- Open the
Production Schedule by Line window. Select one of the production schedules for Part 61–901.
- Right-click and then click Production Receipt to open
Production
Receipt window.
- Select Report Point check box and select a report point by List of
Values.
- Click OK to report production at report point.
- Go back to Inventory Part Currently On Hand window
and refresh. Verify that the inventory level for Part 61–999 has been reduced.
- Open the Production Receipts window.
- Select the line that made the issue of Part 61–999.
- Right-click and then click Reverse Receipt and Reverse Backflush.
- Go back to Inventory Part Currently On Hand window
and refresh. Verify that the inventory level for Part 61–999 has increased.
Reverse Production Receipt—Complete
- Open window Inventory Part Currently On Hand
- Query for Part no 61-999.
- Make a note of the quantity on hand for part 61-999.
- Open the
Production Schedule by Line window. Select one of the production schedules for Part 61–901
.
- Right-click and then click Production Receipt to open
Production
Receipt window.
- Select Complete check box and select the location number from List of
Values.
- Click OK to report production complete.
- Go back to Inventory Part Currently On Hand window.
Query for the parts 61-999 and 61-901. Verify that the inventory level for Part 61–999 has been reduced and
that you have received Part 61–901 into inventory.
- Open the Production Receipts window.
- Verify that there are two lines that made the issue of Part 61–999.
- Right-click and then click Reverse Receipt and Reverse Backflush for the line
on which the report point ID is blank.
- Go back to Inventory Part Currently On Hand window.
Check the inventory level for Parts 61–999 and 61–901.
- Right-click and then click Reverse Receipt and Reverse
Backflush for the line on which the report point ID has a value.
- Go back to Inventory Part Currently On Hand window.
Check the inventory level for Parts 61–999 and 61–901.