Create and Confirm Proposed Schedules—Key Exercise
Basic Data Setup
You should have completed the specified exercise before
you start on this exercise. In this exercise, you have to set up the basic
data that will be
used in this exercise. You must have defined demands for the
production line parts before starting this exercise.
Calculate
Takt Time
Main Exercise
Purpose: The purpose of this lesson is to show you
how to work with production line management in creating proposed production
schedules, and then confirming the proposed schedule as the new current schedule.
Windows:
ProductionLine Management
Create Proposed Schedules
- Open the
Production Line Management window.
- Query for the production line 909.
- Right-click and then click Create Proposed Line
Schedule. In the dialog box that opens, leave the Part No field
blank (indicating that all the parts should be scheduled), select the Load Infinite
schedule generation option, and enter a date range of demands to be
retrieved for scheduling.
- Click OK.
- Click the
Proposed Schedule tab,
and check the results.
Confirm Proposed Schedules
- Right-click and then click Confirm Proposed
Schedule. In the dialog box that opens, leave the Part No field
blank, and specify a date interval of proposed schedules to be confirmed.
Select the
Replace Existing Schedule check box.
- Click OK.
- Click the
Current Schedule tab, and check the results.