Sequencing by Characteristics and Setup Reduction—Key Exercises
IMPORTANT |
It is extremely important that you set up and work within the CBS
training site. If you work within any other site, you will not be
able to access a CBS server. To simplify data entry, select the CBS
site as your default site on the
Sites
per User window. Also, to keep your data separate from
that of other users, be sure to name all data using your initials as the
prefix. |
Basic Data Setup
Overview of Constraint Based Scheduling Data
Purpose: The purpose of this exercise is to create the
required data used in the Constraint Based Scheduling (CBS) exercises. This sets
up data for your site that needs to be done only once for all CBS exercises.
- If you have not done so already, set up your site so that it includes all
the CBS required data.
General exercise for
Overview of Constraint Based Scheduling Data
Main Exercises
Using the Sequencing Wizard
Purpose: The purpose of this lesson is to demonstrate,
using the Sequencing Assistant, how the sequence of operations for a
work center can be determined based on characteristics.
Windows:
Simulation Client
Sequencing Assistant
Note: Before you begin this exercise, create the
additional shop orders listed in the table below. In each shop order number,
replace XX with your initials. Before creating the shop orders, make sure that
the program is set to create shop orders with a status of Planned. This is
specified on the
Parameters
for Distribution and Manufacturing window.
Shop Order |
Part Number |
Schedule Direction |
Earliest Start Date |
Need Date |
Lot Size |
XX–SW1 |
XX–910–C–31 |
Forward |
Monday of next week (e.g., 2/12/01) |
Friday of next week (e.g., 2/16/01) |
50 |
XX–SW2 |
XX–910–C–12 |
Forward |
Monday of next week (e.g., 2/12/01) |
Friday of next week (e.g., 2/16/01) |
50 |
XX–SW3 |
XX–910–C–22 |
Forward |
Monday of next week (e.g., 2/12/01) |
Friday of next week (e.g., 2/16/01) |
50 |
XX–SW4 |
XX–910–C–11 |
Forward |
Monday of next week (e.g., 2/12/01) |
Friday of next week (e.g., 2/16/01) |
50 |
- Reopen or refresh the Simulation Client.
- Hold down the Shift key, and drag Work Center XX700 to the Gantt chart.
- On the Tools menu, click
Settings. The
Settings dialog box appears.
- In the Show area of the Settings/Plot
Settings/Operations tab, verify that the Setup
Times and Names check boxes are selected.
- Open the Sequencing Wizard.
- In the Start Date and End Date fields, enter the date range
during which the sequencing should be performed. Use today's date (e.g.,
2/06/01) for the start date and next Friday's date (e.g., 2/16/01) for the
end date. The default range comes from the Sequencing Horizon (Days)
field in the
Scheduling Basic Data window.
- In the Earliest Start Date field, enter tomorrow's date (e.g.,
2/07/01).
- In the Site field, enter your CBS site name.
- In the Work Center field, enter XX700.
- In the table below, insert a new row. Select the characteristic code 110 as the first sort criteria. Also select the Ascending sort order and Numeric
sort type.
- Click Next to proceed to the Operations To Sequence
window. This window displays the orders and operations affected by the
criteria.
- Choose all the operations to sequence by selecting the Sequence?
check box.
- Click Next to proceed to the next window of the wizard. This window highlights the changes in the number of tardy orders before and
after sequencing. The tardy orders after sequencing appear.
- Click Next to proceed to the Sequencing Results window.
This window displays the results of the new operation sequence for work center
XX700. The lighter colors
are scheduled first.
- Click Finish to save the new schedule.
- Open the Simulation Client. On the File menu, click Open Workspace. Select the file Sequence.fsw, and click Open.
Reducing Setups
Purpose: The purpose of this lesson is to use a work
center setup matrix to define and schedule setup changeover times between
operations with different characteristics.
Windows:
Work Center
Schedule Operations
Simulation Client
Sequencing Assistant
Note: The operations scheduled on the XX700 resource have
an improved sequence, but the setup time of the operations does not reflect
reality. To properly reflect the changeover times between the operations, you
need to define a dependent setup matrix for Work Center XX700.
- Open the
Work Center window, and click the
Setup
Matrix tab.
- Create a new record.
- In the Characteristic Code field, enter 110.
- In the Default Setup Time field, enter 0.25 (hours).
- Save your changes. A dependent setup matrix for the three characteristic
values of Characteristic Code 110 is automatically created.
- Define the setup changeover times as follows:
From Char Value |
To Char Value |
Setup Time |
10 |
10 |
0 |
10 |
20 |
0.25 |
10 |
30 |
0.5 |
20 |
10 |
1 |
20 |
20 |
0 |
20 |
30 |
0.25 |
30 |
10 |
2 |
30 |
20 |
1 |
30 |
30 |
0 |
- Open the
Schedule Operations dialog box to
reschedule the CBS site.
- In the Site field, enter your site.
- In the Dispatch Rule list, click Sort by Earliest Due Date.
- Open or refresh the Simulation Client to view the new
schedule. Plot Work Center XX700 and its resource on the Gantt chart. Note
that the setup times between each operation reflect the changeover times
defined in the setup matrix of the work center. Once again, the sequence of
the operations is not desirable.
- Open the
Scheduling Basic Data window.
- Under Setup Optimization, click Use Part Number. This
indicates that CBS should not schedule a setup when consecutive operations
of the same part or part/operation occur on a work center resource.
- Open the Sequencing Assistant.
- In the Start Date and End Date fields, enter the date range
during which the sequencing should be performed. Use today's date (e.g.,
2/06/01) for the start date and next Friday's date (e.g., 2/16/01) for the
end date.
- In the Earliest Start Date field, enter tomorrow's date (e.g.,
2/07/01).
- In the Site field, enter your CBS site name.
- In the Work Center field, enter XX700.
- Insert a new row in the table below. Select Characteristic Code 110 as the first sort criteria. Also select Ascending as the sort order and
Numeric as the sort type.
- Click Next to proceed to the second window of the wizard.
- Choose all the operations to sequence by selecting the Sequence?
check box.
- Click Next to proceed to the third window of the wizard. Click Next
again to proceed to the fourth window.
- Select Release on all the shop order operations.
- Click Finish to save the new schedule.
- Open the Simulation Client. Verify that the
operations are scheduled in the correct order for Work Center XX700. The
amount of setup time has also been reduced.