Creating Resource Routings—Basic Data and Requirements Exercises

IMPORTANT
It is extremely important that you set up and work within your own site to maintain your data integrity. If you work within any other site, you will compromise your own exercise data as well as the data of other students. Predictable exercise results require that your data be isolated in your own site.

Main Exercise

Create a Resource Routing

Purpose: The purpose of this exercise is to create a resource routing record..

Windows:
Resource Routing

  1. Open the Resource Routing window. 
  2. Create a new record. 
  3. In the Site field, specify the site for which you want to enter resource requirements. Use the List of Values to select from available sites. 
  4. In the Part No field, enter the part for which you want to enter resource requirements. Use the List of Values to select from available parts. 
  5. In the Operation No and Operation Description fields, enter the operation to be performed and a description. 
  6. In the Valid From and Valid To fields, enter the date interval for the operation's validity. Today's date is the default for the start date. If you do not enter an end date, the operation is valid indefinitely. 
  7. In the Parallel Operations field, specify whether the operation is allowed to be planned at the same time as other operations. 
  8. In the Work Center No field, specify the work center where the operation will be performed. The work center can be an active or planning resource. Use the List of Values to select from available work centers. 
  9. Enter the efficiency of the operation in the Efficiency Factor field. 
  10. Enter the resource consumption factor. 
  11. Enter the unit of measure. 
  12. Save the record.