Enter Activity Estimates

Explanation

Use this activity to enter estimated costs, revenues or hours for the activity. Values are entered for project cost/revenue elements.

Prerequisites

System Effects

Window

Project Navigator/Activity/Estimate

Activity/Estimate

Related Window Descriptions

Project Navigator/Activity/Estimate

Activity/Estimate

Procedure

  1. Select the required project activity.
  2. Create a new record on Estimate tab.
  3. Select the appropriate project cost/revenue element from the List of Values, for which estimates are to be entered.
  4. Enter the estimated cost, revenue or hours.
  5. Save your changes.