Connect Change Order to Activity
Explanation
Change Orders registered in IFS Change Management can be connected to
activities, and vice versa.
Prerequisites
- A project activity and Change Order must exist.
System Effects
- A Change Order is connected to a project activity, and vice versa.
- When Engineering Change Order (ECO) actions are added to a Change Order that
has activity connection, the activity is updated with planned hours and progress
information.
- Actual cost, time and progress will be updated on the activity when ECO actions
are performed.
- Activity Connection table will be updated with details of connected change
orders.
- Connected change orders can be accessed from the activity.
Window
Project
Navigator/Connections
Activity/Connections
Related Window Descriptions
Project
Navigator/Connections
Change Orders
Change
Management/Change Order
Procedure
Project
Navigator/Connections
Activity/Connections
- Select the desired activity.
- Select the menu option Connect/Disconnect Object.
- In the Connect/Disconnect Object dialog box select the
Change Order tab.
- Mark the change orders to be connected to the activity.
- Click OK to save the changes and close the dialog box.
Change
Management/Change Order
- Select menu option Project Connection/Connect to Activity.
- Select the desired project activity in the
Connect to Activity dialog box.
- Click OK to save the changes and close the dialog box.