Use this tab to view late purchase orders connected to activities. A purchase order is late when the planned receipt date of the purchase order line is later than the required date of the miscellaneous demand. Alternatively for manually connected purchase order lines, the order is late when the planned receipt date of the purchase order line is later than the early finish date of the activity.