Connect Operations to Tasks

Explanation

This activity is used to connect operations to the tasks on a maintenance order. This is done when there exists a task without any predefined operations. It can also be done when you want to connect additional operations to a task.

When a maintenance order is set to the Under Preparation status, predefined active operations (instructions and subtasks) will be connected to all assigned tasks, and the tasks will be set to the Under Preparation status. However, if predefined operations do not exist for one or more tasks, the task will be set to the Incomplete status instead. At such instances you need to manually connect operations to these tasks before the tasks can be set to the Under Preparation status.

All connected tasks must be in the Under Preparation status before the maintenance order can be released.

Prerequisites

To perform this activity, instructions must exist for the part revision of the serial defined on the task(s) without operations. The task to which the operation is to be connected cannot be in either the Work Done or Finished status.

System Effects

If the distribution type defined on the maintenance order is Execution Logic Structure,

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Maint. Order Str.
Maintenance Order/Maint. Order Str./Operations

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary maintenance order.
  2. Click the Maint. Order Str. tab. Select the required task node in the graphical maintenance order structure.
  3. Click the Operations sub tab and create a new record (F5).
  4. In the Operation ID field, enter the ID of the instruction. Use the List of Values to select a valid value.
  5. Save the information (F12).