View Material Plan Multi-Site
Explanation
This activity is used to view a comprehensive display of the supply and
demand details of an inventory part. The current balanced material plan
depicting the supply and demand details will be shown for the selected part in
accordance with the filter criteria for any registered inventory part. This
information allows you to take appropriate measures to ensure that adequate
quantities of the part are available to meet the demand.
Prerequisites
To perform this activity, master scheduling, project master scheduling,
material requirement planning, project material requirement planning or some
other planning activity must have been performed in order to see the
balanced material plan depicting the supply and demand details.
System Effects
N/A
Window
Material Plan - Multi Site
Related Window Descriptions
Material Plan - Multi Site
Material Plan - Muti Site/Material Planning
Procedure
- Open the Material Plan Multi-Site
window.
- Search for the part for which you want to study the material situation
across sites. Use the List of Values to select a suitable part and a filter
if required.
- Click Refresh. The Material Planning
tab will be populated with current supply and demand data for the part across
all user allowed sites. This will give a comprehensive view of the supply and
demand situation across all user allowed sites. The Part
Info Per Site tab will display the site level situation or site and
project level stock situation of the inventory part.
- Select a row on the Material Planning
tab, right-click and click Supply and Demand Details
to open the corresponding supply and demand and perform planning actions to replan
if necessary.
- Use the filters on the header level to filter the information in the Material Planning
and Part Info Per Site tabs. For example, if you want to view
information related to a particular project, first select the
company, program and project and then click Refresh. Click Clear
to clear the filter criteria if required.