Perform Schedule Analysis

Explanation

This activity is used to view production schedules in a graphical format, and to compare the proposed schedules in relation to the demands, the line rate, and the actual schedules for the same period.

Prerequisites

Production schedules must exist.

System Effects

As a result of this activity you can view schedules in a graphical format.

Window

Production Line Management

Related Window Descriptions

Production Line Management
Production Line Management/Schedule Analysis
Detail

Procedure

  1. Open the Production Line Management window.
  2. Select the required production line that you need to perform the schedule analysis from the Production Line list box.
  3. Click the Schedule Analysis tab.
  4. Select the appropriate data and click Refresh Graph. The graphs will be displayed in the Graphic tab pane.
  5. If you want to get a detailed view of a point in the graph, click on the desired point and the Detail dialog box will display it.