Copy Entire Master Schedule - MS Level 1
Explanation
This activity is used to copy an entire level 1 master schedule from one set to another set, mainly for comparison and simulation purposes.
Prerequisites
To perform this activity, a master schedule set must be created.
System Effects
As a result of this activity, the entire level 1 master schedule is copied to the destination MS set. If there was a master schedule already in the destination set, then it will be replaced.
Window
MS Level 1 Forecast Sets
Related Window Descriptions
MS Level 1 Forecast Sets
Copy Entire Master Schedule - MS Level 1
Procedure
- Open the MS Level 1 Forecast Sets
window.
- Select the master schedule set from which you want to copy the master schedule.
- Right-click and then click Copy Entire Master Schedule. The
Copy Entire Master Schedule - MS Level 1 dialog box opened.
- In the Site or the Part No field, specify the destination MS set that you want your master schedule to be copied.
Click List to select from available sets.
- If copying the entire master schedule for a
project master scheduled part, enter a value in the Project PNG field.
- Click OK.
- Copy process will be executed online and you can view the copied master schedule MS Level 1 by clicking Register Forecast tab on MS Level 1 Part window
by selecting destination MS Set from the MS Set list.