Adjust and Verify Background Job for Recalculations of Post Maintenance Checks

Explanation

This activity is used to view calculated due dates for post maintenance check tasks. You can also use this activity to adjust the execution time of the background job (For more information, refer the online help file Using Background Jobs). At installation, the server process for due calculations for post maintenance checks is set (by default) to execute each day at 8:00 P.M. The background job can also be executed manually for a specific post maintenance check.

Prerequisites

System Effects

Window

Serial Maintenance

Related Window Descriptions

Serial Maintenance
Serial Maintenance/Post Maint

Procedure

Follow this procedure to verify calculated tasks:

  1. Open the Serial Maintenance window.
  2. Query (F3) for the serial for which you want to recalculate post maintenance tasks.
  3. Right-click anywhere in the header of the window and then click Perform Due Calculation to open the Perform Due Calculation dialog box.
  4. Select the Post Maintenance Check check box.
  5. If you want to perform the due calculations for all serials in the serial structure, select the Calculate Entire Structure check box.
  6. To perform the due calculations as a background job, select the Run in Background check box.
  7. Click OK.