MS Level 0 Forecast Sets

[About Forecast]

[To Master Scheduling]

Usage

Use this window to copy a forecast on Level 0 from one master schedule set to another. This lets you revise the forecast before you transfer it to master schedule set 1, which is the set used by MRP, CRP, and Shop Order. You cannot copy or add a forecast if a Level 0 or Level 1 calculation is being run for one of the selected sets. There are other considerations. See the About document for descriptions and explanations.

Activity Diagrams

Perform MS level 0

Activities

Add, copy or reset MS level 0 forecast set
Copy entire master schedule - MS 0