Adjust Split Operations
Explanation
This activity is used to adjust the operation quantities within split operations.
Operations material will be connected only to the parent operation even after
the split or adjust action.
In APB or CBS server solution enabled sites, if there is a material
constraint (finite or always finite material) for the operation and if the
operation is split, the material constraint is connected only to the parent
operation and split operations will not be constrained by the material
constraint.
Prerequisites
To perform this activity, split operations must exist for the shop order.
System Effects
As a result of this activity, operation quantities assigned to the split
operations will be redistributed as the user defines.
Window
Shop Order
Shop Floor Workbench
Shop Order Operations
Related Window Descriptions
Shop Order
Shop Floor Workbench
Shop Order Operations
Adjust Split Operations
Related Visualization Chart Descriptions
Shop Order Machine Load
Shop Order Labor Load
Procedure
To adjust a split operation using
the data view:
- In the
Shop Order window
Operation tab,
Shop Floor Workbench or
Shop Order Operations
window search for the shop order operation in which you want to adjust the operation quantities.
- Select one of the split operations, right-click and click Shop Order
Operation Split/Adjust . This will open the Adjust Split Shop
Order Operations dialog box with all the split operations connected to the
selected operation populated.
- Redistribute the operation quantities on operations by adjusting the
New Qty to Report field.
- Click OK.
To adjust a split operation using
the visualization view:
- Open a visualizer enabled window
and query for the site needed .
- If the Data View is displayed, click
Visualization View on the title bar.
- Right-click and click
Select Visualization.
The
Select Visualization dialog box is
opened.
- Double-click Shop Order
Machine Load or Shop Order Labor Load.
- Right-click and click Y-Axis/Shop Order Operation.
- Select the inner segment
representing the shop order operation you want to adjust, right-click, point
to
Shop Order Operation Split
and then click Adjust. This
will open the
Adjust Split Shop
Order Operations dialog box with all the split operations connected to the
selected operation populated.
- Redistribute the operation quantities on operations by adjusting the
New Qty to Report
field.
- Click
OK.