Maintain Interim Demand Header
Explanation
Use this activity when you want to view or edit an existing interim demand header.
From this activity, you can create or change the configuration, and change the
demand quantity or required date. You can also close the interim demand header,
which will close all of its interim orders, calculate costs, save the standard
cost, and create a DOP from the interim demand structure.
Prerequisites
- IFS/Manufacturing Standards structures and routings should be defined for
the part.
- If configured parts are to be used, IFS/Configuration Characteristics and
IFS/Configuration Back Office must have been installed and associated
configuration characteristics and back office configuration rules defined.
- An interim demand header must be defined.
- The part configuration revision cannot be in Obsolete status.
System Effects
An interim demand is viewed,
reviewed, and edited.
Window
Interim Demand Header
Related Window Descriptions
Interim Demand
Head
Procedure
- From Interim Demand Header, query for the interim demand
header to view or edit.
- Make any changes or perform the desired activities in the window.
- Click Save (F12).