Approve Project Product Design
Explanation
Use the menu option Design to advance a project item from
Defined status to Designed. The menu option Approve Design will change the status from
Defined to Designed. Approve Design affects only the selected item(s) and not the
structure above or below the selected item(s).
Prerequisites
- The project part definition must be approved.
- The project item must be in Defined status (Redefine Project Item)
- The project must have been approved.
- Approval routing for the project item (if used) must have
been completed.
- The standard part must have been released, otherwise
technical characteristics from Part Catalog will be used.
System Effects
- The project item status is set to Designed.
- Designed Date is set to the current date.
- A line is written in the journal.
Window
Project Item Navigator
Related Window Descriptions
Project Item Navigator/General
Procedure
- Select the project item you want to approve.
- Select the menu option Status and sub menu option Approve Design.