This activity is used to manually finish a maintenance order.

Note: It is also possible to automatically set a maintenance order to the Finished status. To enable this automatic status-change you need to select the Automatically Finish Order check box on the maintenance order. When this check box is selected, the status of the maintenance order is set automatically to Finished when the last connected task on the order is set to either the Finished or Cancelled status.

Prerequisites

System Effects

As a result of this activity, the maintenance order is finished and moved to history. If an Execution Logic Structure (ELS) has been created for the maintenance order, this ELS will be removed when the maintenance order is finished.

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Order

Finish Maintenance Order - Dialog Box

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary order number.
  2. Right-click, point to Status, and then click Finish. The Finish Maintenance Order dialog box opens.
  3. In the Finish Date field, enter the date the maintenance order is to be finished. The system date appears by default, but can be changed if needed. Note that the date you change to cannot be earlier than the finish date of the last task on the maintenance order.
  4. Select the Create Snapshot of Maintenance Order check box if you want a snapshot of the maintenance order taken when finishing the order.
  5. In the Snapshot Description field, a default description appears automatically. If needed, you can enter additional information to the existing description or enter a new description in the field. A value in this field is required to be entered if the Create Snapshot of Maintenance Order check box is selected.
  6. Click OK.